Projects

Salvage of Levent S (June 2018)
With: Marine Masters
Description: Re-float of the grounded tug 'Levent S'.
The 640 MT tug was grounded in Qatar waters for several months. Responsibilities:
  1. Grounding analysis.
  2. Stability analysis
  3. On site support

The Ocean Cleanup (Feb2018)
Detailing and review of installation procedures for tow-out and installation of the roaming systems.

Dolwin Gamma (April 2017– July 2017)
Client: Boskalis
Description: Project Engineering and Site Engineering for Boskalis at the Dolwin gamma fender removal project.
With very tight dimensional limitations and stringent weather criteria, six temporary fenders that were required for the topside float-over had to be removed. A barge equipped with a project dedicated ALE crane was positioned under the topside to remove the fenders from the jacket legs. Responsibilities:
  1. Overall responsible for all engineering and procedures.
  2. Obtaining of certificates, approvals and permits
  3. Interfaces with other parties involved like ALE and ACE winches
  4. Barge outfitting

divingbellguide

Diving Bell Wire Centralizer (2016)
Client: Boskalis Subsea Services
Description: Concept engineering and coordination of first phase detailed engineering for a  guiding system that allowed the launch of a diving bell through the moon-pool of the offshore supply vessel “MMA PRESTIGE” with two knots current.

DJI_0009_1

LAM-E jacket and topside (January 2014 – August 2016)
Client: CNGS Group
Description: Engineering for the LAM-E jacket and topside loadout, transport and installation. Installation was done by means of a float-over operation. The work was performed together with Orca-Offshore.
Responsibilities:
  1. Concept engineering and propose alternative concepts
  2. Supply all loads for loadout, transport and mating analysis.
  3. All engineering for the loadout, transport and mating of the LAM-E topside
  4. Advice on equipment required to facilitate the operation.
  5. LMU design
  6. Supervising ballast operations during loadout and mating.

GinaKrog02

Gina Krog Launch Jacket (2013 – Jul 2014)
Client: Heerema Fabrication Group (HFG)
Description: Project engineering activities.
Responsibilities:
  1. Engineering for temporary phases being loadout, transport, launch, upending and set-down
  2. Jacket ballast system.
  3. Operational interfaces with T&I contractor (SAIPEM)

AastaHansteenSpar

Aasta Hansteen Spar and Topside (July 2012 – Dec 2014)
Client: Dockwise
Description: Project engineering activities.
Responsibilities:
  1. Engineering for Spar loadout, transportation and discharge

Valemon

Valemon Jacket (2010 – 2012)
Client: Heerema Fabrication Group (HFG)
Description: Project engineering activities.
Responsibilities:
  1. Ensuring the engineering progress in genera
  2. Engineering for the temporary conditions. Loadout, transport and Lift-off.

LuciusSpar

Heidelberg Spar (2012 – 2014)
Client: Dockwise
Description: Project engineering activities.
Responsibilities:
  1. Engineering for Spar loadout, transportation and discharge

2013-04-17-09-41-44

Lucius Spar (2012 – 2013)
Client: Dockwise
Description: Project engineering activities.
Responsibilities:
  1. Engineering for Spar loadout, transportation and discharge

img_0455

Turkmenistan Block 1 Riser Platform - A (MGR-A) (2012)
Client: ALE
Description: Ballast Engineer at “ALE Heavy Lifting”.
Responsibilities:
  1. Review the ballast and discharge procedures for the discharge of the “MCR-A Gravity Base Structure” with Installation Barge “DAGBASY”
  2. On site guidance on ballasting and discharge float-off operation.

Vyborg float-over (2012)
Client: Dockwise
Description: Project engineer for the Vyborg float-over project.
The global deformation of the lower hull of the SSFDR (Semi-Submersible Floating Drilling Rig) during the mating of the topside on the lower hull and the subsequent impact on a local level was a very challenging issue.
Responsibilities:
  1. Design of the mooring spread.
  2. FE analyses for the interaction between the vessel, the floating hull and the topside during the mating process
  3. Offshore Installation Manual for the mating.
  4. Typhoon avoidance procedures

Goliat_FPSO

Goliat FPSO (July 2010 – January 2011)
Client: Dockwise
Description: Lead engineering for the loadout, transport and discharge.
Responsibilities:
  1. Define the project planning.
  2. Transform concept studies to detailed engineering and finalize the design for transport such that construction can proceed.